15th September 2021
The works on Rocky Lane south of Wendover have been reprogrammed, the full schedule is set out below for clarity but from Monday Rocky Lane will be open under a lane closure and traffic lights for three weeks. The traffic lights will be manned to ensure that traffic doesn’t back up on the A413. A full closure will start from 4th October when the road will be fully excavated meaning that no traffic will be able to get through.
Week 1 – w/c 13th Sept Lane Closure: Rocky Lane Northern Lane
Week 2 – w/c 20th Sept Lane Closure: Rocky Lane Southern Lane
Week 3 – w/c 27th Sept Lane Closure: Rocky Lane Southern Lane
Week 4 – w/c 4th Oct FULL CLOSURE OF ROCKY LANE
Week 5 – w/c 11th Oct FULL CLOSURE OF ROCKY LANE
Week 6 – w/c 18th Oct FULL CLOSURE OF ROCKY LANE