The works on Rocky Lane south of Wendover have been reprogrammed, the full schedule is set out below for clarity but from Monday Rocky Lane will be open under a lane closure and traffic lights for three weeks. The traffic lights will be manned to ensure that traffic doesn’t back up on the A413. A full closure will start from 4th October when the road will be fully excavated meaning that no traffic will be able to get through.


Week 1 – w/c 13th Sept Lane Closure: Rocky Lane Northern Lane

Week 2 – w/c 20th Sept Lane Closure: Rocky Lane Southern Lane

Week 3 – w/c 27th Sept Lane Closure: Rocky Lane Southern Lane

Week 4 – w/c 4th Oct FULL CLOSURE OF ROCKY LANE

Week 5 – w/c 11th Oct FULL CLOSURE OF ROCKY LANE

Week 6 – w/c 18th Oct FULL CLOSURE OF ROCKY LANE