top of page

Notice of work traffic management, A413 Wendover


Notice of work overnight road closure A413 Wendover August 2022
.pdf
Download PDF • 253KB

A message from EKFB:


What are we doing?


In order to build the Small Dean Viaduct, we will be temporarily realigning a section of the A413. To facilitate this realignment, we will be carrying out works adjacent to the Chiltern Railway line and the A413 London Road. For reasons of safety, these works will be carried out overnight while the rail line is not in service.


The temporary re-alignment of the A413 is expected to be operational in early 2023 and the Small Dean Viaduct is expected to be completed in late 2024.


We will be carrying out additional works along the A418 including the diversion of utilities in October 2022. We will update communities in due course.


When will these works take place?


A section of the A413 London Road will be fully closed overnight from 8pm Thursday to 6am Sunday, beginning on Thursday 1 September 2022 for approximately 6 weekends. The diversion will be signposted.


These dates may be subject to change due to circumstances outside of our control, such as weather.

861 views
bottom of page